Building in a bushfire-prone area of Australia? Your Bushfire Attack Level (BAL) decides how your home must be built, and it can add thousands of dollars to the price. Choose your BAL below to see what it means and what it typically adds to the cost of a new home.
The six BAL levels
| BAL | Radiant heat | What it means | Typical extra build cost |
|---|---|---|---|
| BAL-LOW | Insignificant | Very low risk; no specific construction requirements | Nil |
| BAL-12.5 | Up to 12.5 kW/m² | Mainly ember attack | A$13,000 |
| BAL-19 | 12.5–19 kW/m² | Increasing ember attack and burning debris | A$18,500 |
| BAL-29 | 19–29 kW/m² | High risk; more radiant heat | A$21,300 |
| BAL-40 | 29–40 kW/m² | Very high risk; flames may intermittently reach the house | A$57,000 |
| BAL-FZ | Above 40 kW/m² | Flame zone: direct exposure to the fire front | A$69,000 |
Where the figures come from
- BAL levels: CSIRO sets out the heat-flux thresholds for each BAL under Australian Standard AS 3959. The Victorian Building Authority notes that in a designated bushfire-prone area of Victoria, homes must be built to at least BAL-12.5 even if the site is rated BAL-LOW.
- Extra building cost: The City of Gosnells (WA) published average extra costs for a typical home at each BAL in July 2025. The figures came from a project home builder, so treat them as a guide only.
- BAL assessment fee: Nillumbik Shire Council charges A$330 for a BAL report (from 1 July 2024). Private bushfire consultants set their own fees.
What drives the extra cost
The higher the BAL, the stricter the rules for roofs, external walls, windows, doors, decks and subfloors. At lower levels, much of the work is about keeping embers out: sealing gaps, screening windows and vents, and using toughened glass. At BAL-40 and BAL-FZ, windows and doors need fire-rated systems or bushfire shutters, and more of the building must be non-combustible.
Upgrading an existing home
Yarra Ranges Council groups common bushfire upgrades by cost:
- Low cost: sealing small gaps, draught seals at the base of doors, and covering vents and weepholes with metal mesh.
- Moderate cost: shutters or metal flyscreens on doors and windows, toughened glass, solid or non-combustible external doors, and enclosing the subfloor.
- High cost: replacing wall, roof or floor materials with non-combustible ones, sprinkler systems, non-combustible decking and private bushfire shelters.
Ways to keep costs down
- Get your BAL assessed early, before you design, so your plans match the rating.
- Think about where the house sits on the block. Moving it further from vegetation can lower the BAL.
- Ask your builder to price each BAL option. Project builders often have set upgrade packages.
Preparing for other emergencies too? See our disaster-ready home guide and emergency water storage calculator.
Estimates only, for planning. BAL requirements are set by AS 3959 and your state’s building rules; a qualified assessor and your builder or certifier decide what applies to your site. Figures were taken from the linked sources in November 2026 and may change.